Many of the science labs on campus are more than 25 years old. Proposition Community College is helping modernizing our current spaces and expand lab space on campus. Prop CC is also being used to purchase state-of-the-art equipment to best prepare students for the future.

Project List and/or description of projects

St. Charles Community College will renovate the current Café-Bookstore Building to create at least five new science labs along with additional classrooms, offices and student study areas. The renovation will create a more expansive learning environment for our students while also creating the potential for growth in STEM programs. 

View PDF of current plans.

Aug. 2021 - STEM Lab Renderings (DRAFT)

Timeline

  • April 2021 - Programming 
  • April 2021 - Schematic Design 
  • June 2021 - Design Development 
  • Aug. 2021 - Construction Documents 
  • Sept. 2021 - Bidding for General Contractor 
  • Nov. 2021- Construction Begins
  • July 2022 - Construction Complete
  • Aug. 2022 - Classes begin in new Life Science building 

Budget

$5,000,000

Professional Services Team

St. Charles Community College has selected SSC Engineering, Chesterfield and Aspire Construction as the General Contractor to build and to help design the new labs on campus. 