Infrastructure and Modernization of Facilities
Proposition Community College is helping to create a streamlined, modernized environment for student success. The first floor of the Administration Building is in the process of being renovated and transformed into a student-centric space focused on admissions, advising, financial aid, student wellness and more. At the end of the project, students will have a start-to-finish facility to create a simple, seamless intake process for admission.
Project List and/or description of projects
St. Charles Community College will upgrade heating, air conditioning and ventilation
systems on campus and update mechanical, electrical and plumbing systems, creating
a more efficient campus. SCC has selected SSC Engineering, Chesterfield, to help upgrade
HVAC, mechanical, electrical and plumbing on campus.
Additionally, SCC will create new interior and exterior signage throughout campus.
The signage will help improve navigation on campus and create a modern, efficient
way to deliver information to students, faculty, staff and the community.
The projects will:
- Provide appropriate signage to enhance the safety and wellbeing of our campus community.
- Use consistency and design to enhance clarity and identity for our campus community and the community at large.
- Develop wayfinding and directional signage to provide a friendly campus environment.
- Use a signage system that is designed to accommodate updates.
- Select signage with universal design and ADA compliance in mind for an inclusive community environment.
Professional Services Team
SCC has selected Arcturis, St. Louis, to design new interior and exterior signage on campus.
Timeline
- May 2023 - Main Campus Signage (Phase 1) - Completion
- July 2023 - FTTI Building Signage - Completion
- Sept 2023 - DCC LED Sign and Monument - Completion
Budget
$5,100,000